✨ Railway Traffic and Construction Costs




Feb. 4.] THE NEW ZEALAND GAZETTE. 169

COMPARATIVE STATEMENT of TRAFFIC on ALL SECTIONS, from 1st April, 1885, to 2nd January, 1886.

All Sections. Passengers. Season Tickets. Number. Number.
First Class. Second Class. Total. Total.
S. R. S. R.
1886 224,386 331,040 820,211 1,155,522
1885 243,870 289,926 866,543 1,015,230
Inc. .. 41,114 .. 140,292
Dec. 19,484 .. 46,332 ..

TONS.

All Sections. Chaff, &c. Wool. Firewood. Timber. Grain. Merchandise. Minerals. Total.
Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr.
1886 .. 12,215 0 0 41,363 4 0 64,640 0 0 155,786 11 0 327,520 14 0 272,546 4 1 517,557 2 0 1,391,678 15 1
1885 .. 13,970 0 0 32,644 8 0 67,790 0 0 135,082 3 0 357,685 18 1 265,028 13 2 473,104 11 1 1,345,305 14 0
Increase .. 8,718 16 0 .. 20,704 8 0 .. 7,517 10 3 44,452 10 3 46,373 1 1
Decrease 1,705 0 0 .. 3,150 0 0 .. 30,165 4 1 .. .. ..

APPROXIMATE COST of CONSTRUCTION of ALL LINES to 31st March, 1885, including Expenditure on Harbour Works forming part of the Railway System.

Section. Gross Cost of Opened and Unopened Lines. Cost of Opened Lines.
Β£ s. d. Β£ s. d.
Kawakawa .. .. .. .. .. 86,283 0 0 86,283 0 0
Whangarei-Kamo .. .. .. .. .. 64,032 0 0 64,032 0 0
Auckland .. .. .. .. .. 1,349,672 0 0 1,319,672 0 0
Waikato-Thames .. .. .. .. .. 74,000 0 0 ..
Main Trunk Line, North Island .. .. .. .. .. 2,441 0 0 ..
Napier .. .. .. .. .. 551,213 0 0 551,218 0 0
Wellington .. .. .. .. .. 849,714 0 0 799,714 0 0
Wanganui .. .. .. .. .. 1,334,573 0 0 1,334,573 0 0
Wellington-Manawatu .. .. .. .. .. 41,404 0 0 ..
Surveys, North Island .. .. .. .. .. 16,612 0 0 ..
Miscellaneous .. .. .. .. .. 5,168 0 0 ..
Hurunui-Bluff .. .. .. .. .. 7,201,507 0 0 6,890,118 0 0
Greymouth .. .. .. .. .. 192,975 0 0 176,975 0 0
Greymouth-Hokitika .. .. .. .. .. 30,200 0 0 ..
Grey Harbour Works .. .. .. .. .. 127,018 0 0 ..
Westport .. .. .. .. .. 210,886 0 0 210,886 0 0
Westport Harbour Works .. .. .. .. .. 13,593 0 0 ..
Nelson .. .. .. .. .. 171,990 0 0 164,490 0 0
Picton .. .. .. .. .. 228,233 0 0 212,233 0 0
Surveys, Middle Island .. .. .. .. .. 36,117 0 0 ..
Miscellaneous .. .. .. .. .. 5,168 0 0 ..
Stock .. .. .. .. .. 263,823 0 0 ..
Total .. .. .. .. .. 12,856,627 0 0 11,810,194 0 0

Railway Department, 3rd February, 1886. J. P. MAXWELL, General Manager, New Zealand Railways.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 1886, No 6





✨ LLM interpretation of page content

πŸš‚ Comparative Statement of Traffic on All Sections (continued from previous page)

πŸš‚ Transport & Communications
4 February 1886
Railway, Traffic, Passengers, Parcels, Livestock, Tons, Chaff, Wool, Firewood, Timber, Grain, Merchandise, Minerals
  • J. P. Maxwell, General Manager, New Zealand Railways

πŸš‚ Approximate Cost of Construction of All Lines (continued from previous page)

πŸš‚ Transport & Communications
4 February 1886
Railway, Construction, Costs, Lines, Sections, North Island, Middle Island, Harbour Works
  • J. P. Maxwell, General Manager, New Zealand Railways