July 8.] THE NEW ZEALAND GAZETTE. 829

COMPARATIVE STATEMENT of TRAFFIC on ALL SECTIONS, from 1st April, 1886, to 29th May, 1886.

All Sections. Passengers. Season Tickets. Number. Number.
First Class. Second Class. Total. Total. Parcels. Horses. Carriages. Dogs. Total. Drays, &c. Cattle. Calves. Sheep. Pigs.
S. R. S. R.
1886 43,870 88,042 160,949 302,558 595,419 2,178 53,531 1,888 114 4,686 60,219 98 5,066 415 151,585 13,556
1885 48,145 66,224 179,749 215,108 509,226 1,782 46,614 1,741 107 4,497 52,959 112 4,842 398 131,790 9,273
Inc. .. 21,818 .. 87,450 86,193 396 6,917 147 7 189 7,260 .. 224 17 19,795 4,283
Dec. 4,275 .. 18,800 .. .. .. .. .. .. .. .. 14 .. .. .. ..

Tons.

All Sections. Chaff, &c. Wool. Firewood. Timber. Grain. Merchandise. Minerals. Total.
Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr. Tons c. qr.
1886 .. 3,055 0 0 4,650 4 0 12,790 0 0 29,023 1 0 96,602 0 0 55,690 16 2 108,789 19 2 310,601 1 0
1885 .. 2,100 0 0 4,332 0 0 13,820 0 0 28,675 14 0 117,068 3 1 58,042 19 2 99,275 18 1 323,314 15 0
Increase 955 0 0 318 4 0 .. 347 7 0 .. .. 9,514 1 1 ..
Decrease .. .. 1,030 0 0 .. 20,466 3 1 2,352 3 0 .. 12,713 14 0

STATEMENT showing Cost of Construction of ALL LINES, GENERAL GOVERNMENT, PROVINCIAL, and DISTRICT RAILWAYS, to 31st March, 1886, including Expenditure on Harbour Works constructed from the Railway Votes.

Section. Gross Cost of Opened and Unopened Lines. Cost of Opened Lines.
Β£ s. d. Β£ s. d.
Kawakawa .. .. .. .. 89,441 0 0 89,441 0 0
Whangarei-Kamo .. .. .. .. 68,241 0 0 68,241 0 0
Auckland .. .. .. .. 1,586,568 0 0 1,545,181 0 0
Waikato-Thames .. .. .. .. 40,050 0 0 ..
Main Trunk Line, North Island .. .. .. .. 60,780 0 0 ..
Napier .. .. .. .. 571,909 0 0 559,800 0 0
Wellington .. .. .. .. 907,762 0 0 815,000 0 0
Wanganui .. .. .. .. 1,368,230 0 0 1,349,900 0 0
Wellington-Manawatu .. .. .. .. 41,815 0 0 ..
Surveys, North Island .. .. .. .. 17,129 0 0 ..
Miscellaneous .. .. .. .. 5,168 0 0 ..
Hurunui-Bluff .. .. .. .. 7,643,238 0 0 7,288,049 0 0
Greymouth .. .. .. .. 196,259 0 0 180,300 0 0
Greymouth-Hokitika .. .. .. .. 37,777 0 0 ..
Grey Harbour Works .. .. .. .. 127,230 0 0 ..
Westport .. .. .. .. 214,402 0 0 214,402 0 0
Westport Harbour Works .. .. .. .. 14,111 0 0 ..
Nelson .. .. .. .. 174,914 0 0 166,700 0 0
Picton .. .. .. .. 219,605 0 0 195,800 0 0
Surveys, Middle Island .. .. .. .. 36,117 0 0 ..
Miscellaneous .. .. .. .. 5,169 0 0 ..
Stock .. .. .. .. 300,241 0 0 ..
Total .. .. .. .. 13,726,166 0 0 12,472,814 0 0

Railway Department, 29th June, 1886. J. P. MAXWELL, General Manager, New Zealand Railways.



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF NZ Gazette 1886, No 37





✨ LLM interpretation of page content

πŸš‚ Comparative Statement of Railway Traffic (continued from previous page)

πŸš‚ Transport & Communications
29 June 1886
Railways, Traffic, Passengers, Parcels, Animals, 1886, 1885

πŸ—οΈ Cost of Construction of Railways

πŸ—οΈ Infrastructure & Public Works
29 June 1886
Railways, Construction, Costs, Lines, Government, Provincial, District, 1886
  • J. P. Maxwell, General Manager, New Zealand Railways