Road Construction Report




ABSTRACT OF LABOUR EMPLOYED, WORK DONE, AND EXPENSE INCURRED ON THE WAIRARAPA ROAD, UNDER MR. H. FITZGERALD, FROM THE 1st OCTOBER TO THE 31st DECEMBER, 1848.

To Surveyors.

PARTICULARS OF THE WORK.

Part employed beyond the first or initial alignments fixed by Captain Smith ... 39 1/2 miles at £9 per lineal mile ...
Part employed beyond the second alignments fixed by Captain Smith ... 39 1/2 miles at £4 10s. per lineal mile ...
Falling very steep over 100 feet per mile ... 18 miles at £3 extra ...
No part completed.

| Total ... | 118 14 0 |
| Ballasting and forming road, and gravelling same ... | 47 chains at 5s. per chain ... | 11 15 0 |
| Length of Road on which the party has been employed ... | 1 3/4 miles |

Number and description of persons employed in connection with the Party, the actual number employed of each class being calculated as so many of that class for one day.

Number.
Superintending Party.
Henry and Rankin ... 1
Surveying Party.
Cassidy temporarily ... 1
Foremen.
O’Reillys ... 2
Overseers.
Civilans ... 2
Mechanics.
Europeans ... 3
Labourers.
Europeans ... 147
Maories employed as Labourers ... 118

SUPERINTENDENTS AND FOREMEN.

Number employed for one day.
Superintendents ... 95
Foremen ... 59

LENGTH OF ROAD.

Length of Road on which the party has been employed ...
Width of the Road ...
Distance the Carts have to go for Stone or Timber ...

GENERAL CHARACTER OF THE WORK.

Description of tools used during the period.

  • The expense of Tools, during the past quarter amounted to £2 18s. 11d., which has been added to the total value of Implements on charge.

PAYMENTS.

£ s. d.
Pay of Superintendents, Foremen, and Overseers ... 86 11 3
Pay of Mechanics ... 104 1 4
Pay of Labourers ... 163 19 11
Payments for Cartage ... 12 13 1
Payments for contingencies and contracts ... 15 15 6

| Total Payments ... | 383 11 1 |

NOTES ON WORK DONE.

  • Building small Wairarapa road bridge, and clearing 1 1/2 miles of road and track.
  • Building 2nd Two Mile Bank and drain along the road, and making ford and ferry for the Mangaone stream.
  • Building stone and rough wooden bridges over gullies on the 3rd 11 chains of road, covering culverts, and 1 mile forming.

Character, size, extent, etc. of any particular portion of the Work completed during the mentioned period.

  • Felling and burning for road ...
  • Grubbing and clearing ...
  • Earthworks for 30 feet width ...


Next Page →



Online Sources for this page:

VUW Te Waharoa PDF New Munster Gazette 1849, No 4





✨ LLM interpretation of page content

🏗️ Abstract of Labour and Expenses on Wairarapa Road

🏗️ Infrastructure & Public Works
Road construction, Wairarapa Road, Labour, Expenses, Surveyors, Workers, Tools, Payments
10 names identified
  • H. Fitzgerald (Mr), Superintendent of Wairarapa Road
  • Captain Smith (Captain), Surveyor
  • Henry, Superintendent
  • Rankin, Superintendent
  • Cassidy, Surveyor
  • O’Reillys, Foremen
  • Civilans, Overseers
  • Europeans, Mechanics
  • Europeans, Labourers
  • Maories, Labourers