Railway Construction Estimates




ESTIMATED COST OF LAND AND FENCING—

62 Town Sections, Picton
2 Village Sections, Tua Marina

54 sections, average at £40 ... £ 2,160 0 0

90 acres Rural Land, for Line and Stations, at £5 ... 450 0 0

TOTAL LAND ... 2,610 0 0

Fencing from Picton Harbour to the end of steep gradient
at 2 miles 50 chains, and from Tua Marina
Viaduct to Wairau River—
900 chains of Single Fence, post and four rails, at 22s. per chain ... 990 0 0

£3,600 0 0


ESTIMATED COST—CONSTRUCTION OF RAILWAY—

Clearing Timber, 650 chains at £1 ... 650 0 0

Earthwork, as per abstract ... 15,000 0 0

Bridges, Viaducts, and Level Crossings, as per detailed list ... 6,200 0 0

Culverts, 77 ... 1,550 0 0

Main Drains ... 750 0 0

Permanent Way and Ballast, 15 miles, at £1,200 ... 18,000 0 0

TOTAL RAILWAY PROPER ... £42,150 0 0


ABSTRACT OF EARTHWORK—

Principal Cuttings and Side Cuttings—

10,106 cubic yards, at 9d. ... 379 0 0

27,743 „ at 1s. ... 1,387 0 0

46,165 „ at 1s. 3d. ... 2,885 0 0

44,341 „ at 1s. 6d. ... 3,325 0 0

7,990 „ at 2s. ... 799 0 0

5,000 „ at 2s. 6d. ... 625 0 0

2,000 „ at 3s. ... 300 0 0

870 „ at 5s. ... 218 0 0

10,200 „ at 6s. ... 3,060 0 0

154,415 cubic yards ... 12,978 0 0

Sundry small Cuttings and Embankments ... 1,368 0 0

Levelling Ground, 248 chains, at £1 ... 248 0 0

Cartage of Rails for Temporary Ways and Sundries ... 406 0 0

TOTAL EARTHWORK ... £15,000 0 0


BRIDGES, VIADUCTS, AND LEVEL CROSSINGS—

Bridges—

Waiotahi Stream Viaduct, 5 chains ... 2,000 0 0

Kent-street, 5 spans, 24 feet ... 450 0 0

Durham-street ... 150 0 0

Dorset-street ... 150 0 0

Wairau-road ... 205 0 0

River Tua Marina ... 50 0 0

River ... 50 0 0

Channel for Torrent ... 50 0 0

Shingle Stream ... 40 0 0

Stockyard Stream ... 20 0 0

Tua Marina Viaduct, 10 chains ... 1,980 0 0

Wairau Road ... 195 0 0

Brownie’s Creek ... 100 0 0

TOTAL BRIDGES ... £5,440 0 0



Next Page →



Online Sources for this page:

VUW Te Waharoa PDF Marlborough Provincial Gazette 1861, No 17





✨ LLM interpretation of page content

🏗️ Estimates and Evidence for Picton and Wairau Railway (continued from previous page)

🏗️ Infrastructure & Public Works
17 May 1861
Railway, Construction, Estimates, Picton, Wairau, Marlborough